Technical Bulletin
Baldor AC or SWEO AC Drive Availability
Advisory
Date
October 1, 2004
Reference
138
Route to
Modernization Manager/Service Manager
From
MCE Technical Support Manager
Equipment
All MCE equipment supplied with any Baldor AC or SWEO AC
drive.
Description
While Baldor Electric Inc., still manufactures and supports their
AC elevator drives, many drive models are not stocked in regular
quantities and may have manufacturing lead times of up to 8
weeks.
Action
IMPORTANT: If an elevator is shut down due to a Baldor
Drive failure it may take up to 8 weeks to have the system back in
service. If you have a mission critical elevator that cannot
tolerate a prolonged shutdown, we recommend that you bring this to
the attention of the building owners. MCE has tried to provide
alternate solutions in case of drive failure. The solutions we have
identified are listed below. For highly mission critical
applications, we recommend that you purchase a spare drive
unit.
Repair: Baldor does still offer repair service for these
drives. To schedule a repair, MCE customers should call MCE
technical support at the number below. Alternately, there are many
Baldor Authorized Repair Centers around the country that can be
located by zip code at http://www.baldor.com/. These
repair centers can be contacted directly without the involvement of
MCE or Baldor. The repair process could take 1-3 weeks or more
depending on the repair center chosen.
Replace with a New Baldor AC drive: Call MCE for price and
lead time. Note that lead times can be as long as 8 weeks.
Replace with non-Baldor AC drive: In many cases, MCE
offers Magnetek or Yaskawa as a field replacement for the Baldor AC
drive. Call MCE for price and lead time. Please note that this
option requires a controller modification and drive adjustment, and
may take 1-3 weeks to complete.
Help
Should you require additional technical assistance:
- Telephone 916/463-9200
- Touch "6" for Technical Support
Refer to the reference number above
|